Project Timeline

Begin study area evaluation:  Summer 2012
   
Study area open houses: Summer 2012
   
Develop potential routes: Fall 2012
   
Preliminary route network open houses: Winter 2013
   
Reduce route network: Winter/Spring 2013
   
Review route network: Winter / Spring 2013
   
Preferred routes open houses: Spring 2013
   
Selection of final route: Summer 2013
   
Environmental permits completed: Winter 2014
   
Construction begins: Summer 2015
   
Estimated in-service date: Summer 2017